Murray Middle School in Stuart breaks ground on $33M rebuild
A Hurricane Milton tornado wrecked the campus in 2024. The new buildings are expected by December 2027, school officials say.

By the numbers
Murray Middle School in Stuart broke ground Oct. 27 on an approximately $33 million phase of its campus rebuild, the Martin County School District says. The gym is expected to be finished by August 2027 and the new buildings by December 2027, according to school officials cited by WPTV.
The project comes about two years after an EF-1 tornado spawned by Hurricane Milton hit the campus on Oct. 9, 2024. Hedrick Brothers Construction, the construction manager, says the storm destroyed two buildings and caused major roof damage to a third. The district says it displaced the band, choir and agriculture programs.
What Murray Middle School in Stuart is getting
The district says this phase includes:
- New spaces for band, chorus, art and agriculture science
- A modern media center and updated administrative offices
- Gym renovations
- Better parking and student drop-off areas
Hedrick Brothers says it’s replacing Buildings 9, 10 and 18 and adding an upgraded chiller plant for campuswide climate control. Principal Tiffany Roth told WPTV the band and choir rooms will sit in a performing arts wing.
60 years of drama props
The storm took more than classrooms. “It was 60 years of drama props,” Dr. Anita Caswell, the school’s choir and drama director, told WPTV.
Her choir kept singing in a portable classroom. Caswell told WPTV the group earned straight superior ratings that year “even in the small portable.”
Superintendent Michael Maine told WPTV the district already had plans to improve Murray before the storm. The district says the same thing on its site.
Who’s paying, and what’s next
Hedrick Brothers says the project is funded through state support, insurance reimbursements and district capital funds. The district says Gov. Ron DeSantis and the Florida Legislature approved $500,000 for the rebuild in 2025.
Demolition started in July 2026 with Buildings 10 and 18, according to Hedrick Brothers. The school stays open during the work, with construction areas kept separate from students, CBS12 reports.
Did you go to Murray Middle? Tell us your Murray Lions memory on @the772fl.
Sources: Martin County School District, Oct. 30, 2026; WPTV, Oct. 28, 2026; Hedrick Brothers Construction, Oct. 30, 2026; CBS12, Oct. 28, 2026.