Atlantic Point Marina in Stuart will stand on 1,660 piles

The $62.5 million marina by the Roosevelt Bridge needs 65-foot piles and turns its old pier into fill. Opening is targeted for fall 2027.

Architectural rendering of the planned Atlantic Point Marina waterfront in Stuart at night.
Rendering: birse/thomas, via Resilient Marinas. Planned Atlantic Point Marina, not a photo.

By the numbers

1,660Helical piles, per Miller Construction
$62.5MProject cost, per Connect CRE
Fall 2027Target opening, per Resilient Marinas

Atlantic Point Marina in Stuart will stand on 1,660 helical piles, each 65 feet long, builder Miller Construction says in a company release Citybiz published Nov. 17, 2026. Connect CRE reported the same day that the waterfront project costs $62.5 million.

Owner Resilient Marinas says construction broke ground in October 2025 and targets a fall 2027 opening.

Atlantic Point Marina Stuart: what holds it up

Miller says existing soil conditions call for the piles under all three buildings: the boat barn, the ship’s store and the restaurant. President and CEO Brian Sudduth calls the job “an engineering challenge” in the release.

Connect CRE puts the boat barn at 109,584 square feet, built to store boats up to 50 feet long. It lists the ship’s store at 4,000 square feet and the open-air restaurant at 3,625 square feet. The project is a joint venture of Seven Kings Holdings and Resilient Marinas, Connect CRE reports.

The old pier becomes fill

Building the in-water marina means dredging about 42,000 cubic yards of soil after the old breakwater pier comes down, Miller says. The company says the dredged soil is dried on land, blended with crushed concrete from that pier and used as engineered fill to raise parts of the site.

Where it stands

Marina Dock Age reported Sept. 30, 2026, that the dry-stack building’s concrete walls were up and its roof supports were near completion. The site, at the north end of the Roosevelt Bridge on the St. Lucie River, was once an Evinrude Outboard Motors test facility, the magazine says. It reported wet-slip docks are set for installation by February 2027 by Stuart-based Brothers’ Construction.

On Nov. 9, 2026, Stuart city commissioners voted 4-1 to approve a minor amendment to the project, Hometown News reported. Seven Kings CEO Ray Graziotto said the changes cover a sidewalk, parking, underground fuel storage and dock layout, without adding density. Neighbors at the Harborage Yacht Club complained about construction dust and dirt, and Commissioner Sean Reed cast the no vote. Graziotto said the approval conditions require the developer to repair any damage.

Resilient Marinas lists more than 350 dry-storage slips, about 100 wet slips, a fuel dock, ship store and waterfront restaurant. The marina’s own site says it opens in late 2027.

Which would you use: a wet slip or dry storage? Tell us on @the772fl.

Sources: Citybiz, Miller Construction release, Nov. 17, 2026; Connect CRE, Nov. 17, 2026; Hometown News, Nov. 16, 2026; Marina Dock Age, Sept. 30, 2026; Resilient Marinas and Atlantic Point Marina, accessed Nov. 18, 2026.

The 772 Business Brief

One email a week on who's building the Treasure Coast.

The big story, three businesses to know, what's new, and quick hits. About five minutes to read. Sign up and get 25 AI Prompts for 772 Business Owners, free.

Free. Weekly. Unsubscribe anytime.